In order to increase the productivity of the Mexborough site, HB Projects were appointed to develop, design, and install a third bagel production line while maintaining full production from the existing two lines.
Scope of works included full architectural and engineering design, 19,500ft2² mezzanine, internal piled foundations, polyurethane resin flooring, stainless steel kerbing, hygienic walling and ceilings.
We provided a service/trucking corridor with bespoke service support system, full M&E design and installation and external high level plant deck. HB Projects was responsible as Principal Contractor for the post-build plant installation phase and food facility construction standards (dust and fume suppression/elimination).