• Client: Arla Foods
  • Location: Nationwide
  • Project: Modifications, Repairs and Installations
  • Value: Various
  • Duration: 26 weeks
  • Description:

Following a complete rebranding programme, Arla Foods required a programme of works which involved security upgrades and external works.

We worked closely with Arla’s Foods project teams so that the works did not affect distribution and logistics. Weekend working and careful delivery planning helped to minimise disruption.

Summary of scope of works:
  • Electrical services upgrade
  • Installation of automated security barriers
  • Installation of stainless steel drainage
  • Supply and installation of smoking shelters
  • Car park re-surfacing
  • Modifications to goods In entrances
  • New site signage
  • Pedestrian walkways
  • Armco barrier installation

The work was completed ahead of schedule and on budget. Arla’s sites are now more secure and the traffic management has improved the Goods In and Out access road. Our works have ensured a safer environment for pedestrians and all sites are now fully compliant with smoking regulations.