• Client: Asda
  • Location: Accrington
  • Project: Refurbishment
  • Value: 350k
  • Duration: 12 weeks
  • Description:

This is another of the many projects we have delivered under the ongoing ‘Store Refresh’ programme for Asda. The ten-week project saw extensive refurbishments and replacements across the store.

Summary of scope of works:

Delicatessen
Removal of mid-floor deli to allow install of new refrigeration cases

  • Customer service desk and kiosk
  • George Gtwo5 area
  • Toilet lobby area
  • Entrance doors
  • Customer café
  • Colleagues canteen
  • Decorations throughout the sales floor and externally

    All this was done in a live environment with solid hoardings used to close areas off throughout the duration of the scheme.
    Another great looking end result that has received excellent feedback from the client.